The Milne Road Bridge Replacement
Thanks to Mr. Walter Schmid, Bracebridge Public Works Engineer, who has provided the following information. Replacement of Milne Road Bridge will commence between December 9 – 13, 2013. During this time period, Milne Road Bridge will be open for vehicular and pedestrian traffic.
On December 17, 2013 between the hours of 7:00 AM and 7:00 PM, the bridge installation will take place. During this time period, vehicular traffic will NOT be able to cross the creek. However, emergency services will continue to be provided.
Please note that the above dates are part of the anticipated schedule for the bridge replacement. The schedule may change due to inclement weather.