Inspection of the Milne Road bridge abutments
An up date on August 28, 2013 excavation of the Milne Road bridge abutments to determine there conditions. I stopped to see the progress and spoke with a Bracebridge Public Works Engineer.
This is preliminary, and a final report will be prepared by PW and it MAY be available at the next General Committee Meeting or council meeting. You can check the Bracebridge web site and see if the Milne Road Bridge is on either Meetings agenda.
The inspection made on the North Abutment from what I was told the concrete is deteriorating (crumbling) badly and there is a crack in the abutment. The South end was not excavated as it was determined that it would exhibit the same condition as the North.
I would suggest that you forward this email to anyone who is impacted by the deteriorating bridge